Concrete Slab thickness for CNC Machines
#1
Posted 26 July 2012 - 05:48 PM
I just was told that the place only has a 4" slab floor and now I'm getting nervous. Our biggest machine is a 60,000lb Okuma HMC. 4" seems pretty thin to me.
#2
Posted 26 July 2012 - 06:30 PM
#3
Posted 26 July 2012 - 07:18 PM
The machine will probably be fine if the floor is old, and you anchor it nicely. The issue will be the poor little Haas Mini-mill (or any other machine) that's sitting next to it, trying to cut a finish pass when that 60,000lb Okuma is changing pallets.
#4
Posted 26 July 2012 - 07:20 PM
found this online on a very quick search. 4" sounds too thin to me... I think you are right to be a little concerned.
Brendan
#5
Posted 27 July 2012 - 12:20 AM
Worked at a place that had new floor put in, and the contractors just cut straight through the drains. So when it rained, the water had nowhere to go except to saturate the slab which lifted the very expensive epoxy floor coating (non breathable).
4" can be ok and I wouldn't have any probs putting a machine onto some 3/4 boiler plate pads (12" square). Spreads the load over area and all that.
Putting 2ft thick slabs is ok, providing the soil below the slab is ok. No good pouring onto quicksand...just means the whole slab moves.
#6
Posted 27 July 2012 - 05:21 AM
Jerry
#7
Posted 27 July 2012 - 05:32 AM
JerryBenoit, on 27 July 2012 - 05:21 AM, said:
Jerry
Have we worked in the same shop perhaps
We put a new Mori NV5000 on the floor, the standard floor was 4", we dug out and iirc, we had poured a 12" concrete and rebar pad, it may have been closer to 18 but it's been awhile. Another place I worked, and Okuma LC-40, a solid 18 of concrete and rebar.
4" is NOT going to do it, it "might" hold depending what's under it but you'll chase tolerance and machine squareness ALL the time.
#8
Posted 27 July 2012 - 05:55 AM
Mike
#9
Posted 27 July 2012 - 08:38 AM
JParis, on 27 July 2012 - 05:32 AM, said:
We put a new Mori NV5000 on the floor, the standard floor was 4", we dug out and iirc, we had poured a 12" concrete and rebar pad, it may have been closer to 18 but it's been awhile. Another place I worked, and Okuma LC-40, a solid 18 of concrete and rebar.
4" is NOT going to do it, it "might" hold depending what's under it but you'll chase tolerance and machine squareness ALL the time.
Yep. The neys have it. A 4" slab a happy CNC machine does not make especially after reading this:
http://www.emasterca...=1
My manager is bringing this up at a meeting with the biggies on Monday. Should be interesting.
#10 Guest_CNC Apps Guy 1_*
Posted 27 July 2012 - 08:45 AM
For a 65k# machine, you're probably lookign at 18~24" with rebar and anchors, etc...
This is the one area I see sooooooooooo many people skimp on, and of course, when the machines hav issues it's because the machine is a POS not the fact it's on a potato-chip thick floor. I see it all the time, flatness and squareness issues, machine vibrates, etc...
DO A PROPER FLOOR!!!!!!!!
#11
Posted 27 July 2012 - 09:04 AM
Another alternative would be to use a large plate that would disperse the load a little, but even that isn't a great idea.
#12 Guest_CNC Apps Guy 1_*
Posted 27 July 2012 - 09:20 AM
spade117, on 27 July 2012 - 09:04 AM, said:
Another alternative would be to use a large plate that would disperse the load a little, but even that isn't a great idea.
We do this at trade shows often when we're on 2nd floors. Good TEMPORARY solution.
#13
Posted 27 July 2012 - 09:25 AM
As James said, the specs should be in the machines installation manual.
I'm guessing they'll want at least 3ft of concrete. Someone else mentioned the water table
If you've got a high water table, you'll have problems as well.
I've seen a machine sitting on a 15ft thick slab of concrete, that was really floating on the water table.
It was a big gantry mill, and a laser tracker could see it moving up and down along it's X axis as you
rapided back and forth.
It will cost some $$$ up front but if you don't do it, you will pay for not doing it EVERY SINGLE DAY.
We just put in a big VTL ( 200 hp 140" table 900K pounds)
They dug a hole 50 feet deep, lined the walls with a double row of cinderblock and poured 30 ft of concrete.
The foundations cost $80K.
The machine tool builder deemed it marginal but acceptable..
#14
Posted 27 July 2012 - 02:21 PM
#15
Posted 27 July 2012 - 02:24 PM
If the soil sample (ie under the slab) is good, I wouldn't hesitate to put a 40" size vertical on a 4" sat on boiler plate.
But 60000lbs requires a serious floor.
#16
Posted 27 July 2012 - 03:34 PM
#17
Posted 27 July 2012 - 03:37 PM
Crazy^Millman, on 27 July 2012 - 03:34 PM, said:
I don't know.. the foundation was done and they were building the machine when I started.
The number I got was $8 million complete, but I don't know how much of that was foundation
#18
Posted 28 July 2012 - 12:49 AM
You chaps got a pic/link for that machine? What a beastie.
#19
Posted 28 July 2012 - 06:55 AM
Quote
http://jcmcorp.com/w...4_900x600.jpg
#20
Posted 28 July 2012 - 08:45 AM
How do you get on with coolant / swarf flying everywhere with this style of machine?
Also, any ingress into the ways or motors (the red caps look very exposed)?















